Deck Work Status / Schedule

This is a regularly updated list of decks in progress, scheduled, and completed. For project details, click here.

Last Updated: 2020-08-24

In Progress

Scheduled

Install new top coats and waterproofing: Bldg 50, Units 12, 14, 15 waterproofed.
(Invoice 1393 / Check 1186) – Pending

Deck top coating: Bldg 56 Units 4, 7, 8, 9. + Bldg 74 Units 4, 7, 8, 9. + Bldg 86 Unit 13.
(Invoice 1394 / Check 1187) – Pending

Install waterproofing systems: Bldg 86 Units 12, 10. + Bldg 92 Units 4, 5, 8, 9 top coats.
(Invoice 1395 / Check 1188) – Pending

Top coat application Bldg 98 Units 4, 5, 8, 9. + Bldg 104 Unit 15, 16. + Bldg 122 Units 4, 5, 8, 9.
(Invoice 1396 / Check 1189) – Pending

Bldg 110 Units 11, 12.
Bldg 116 Units 11, 12, 13.
Bldg 152 Units 8, 9.
Bldg 158 Units 4, 5, 8, 9.
Bldg 68 Units 4, 7, 8, 9.
Bldg 62 Units 4, 7, 8, 9.
(Invoice 1398 / Check 1191) – Pending

Top coats:
Bldg 128 Unit 4.
Bldg 134 Unit 4.
Bldg 110 Unit 8, 12, 13.
Bldg 140 Units 4, 5, 8, 9.
Bldg 146 Units 5, 8, 9.
Bldg 158 Units 4, 5, 8, 9.
(Invoice 1397 / Check 1190) – Pending

Phase 2 – Completed (Private Balconies – Varied Scope)

Phase 1 – Completed (New Waterproofing System Installed – Main Decks)

104 #5 – Completed on Jan 10, 2020 (Paid)
110 #11 & 13 – Completed Jan 17, 2020 (Paid)
56 #5 & 8 – Completed on Jan 24, 2020 (Paid)
50 #13 & 14 – Completed on Feb 14, 2020 (Paid)
86 #9 & 10 – Completed on Feb 21, 2020 (Paid)
92 #5 & 6 – Completed Feb 28, 2020 (Paid)
98 #4 & 8 – Completed March 6, 2020 (Paid)
146 #7 & 9 – Completed May 22, 2020 (Paid)
104 #14 & 16 – Completed May 29, 2020 (Paid)
104 #11 & 122 # 8 – Completed June 5, 2020 (Paid)
122 #4 & 128 #5 – Completed June 12, 2020 (Paid)
122 #5 & 6 – Completed June 19, 2020 (Inv 1361, Check 1168) Paid
128 #4 & 6 – Completed June 26, 2020 (Inv 1362, Check 1170) Paid
134 #5 & 7 – Completed July 3, 2020 (Inv 1363, Check 1172) Paid
152 #4 & 6 – Completed July 10, 2020 (Inv 1364, Check 1174) Paid
152 #5 & 158 #8 – Completed July 17, 2020 (Inv 1365, Check 1177) Paid
158 #5 & 6 – Completed July 25, 2020 (Inv 1366, Check 1178) Paid
62 #5 & 8 – Completed July 31, 2020 (Inv 1372, Check 1181) Paid
62 #7 & 110 #12 – Completed Aug 7 , 2020 (Inv 1373, Check 1182) Paid
116 #8 & 68 #4 – Completed August 14 (Inv 1374, Check 1184) Paid
68 #6 & 9 – Completed August 21 (Inv 1375, Check 1183) Paid

Notes

1393-1186-5000
1394-1187-6200
1395-1188-6210
1396-1189-7000
1398-1191-13300
1397-1190-11200