The Association has hired Top Armor to complete re-roofing of all the buildings at Casa De Oaks. Work began on 12/2/2024. Notices will be provided to residents in advance of work beginning on their building. The entire project is expected to take approximately 8-10 months.
Top Armor provided the below Phase 1 Schedule on 12/2/2024, which is considered an estimate, and all dates are weather permitting. Again, notices will be provided to residents in advance of work.
Sequence | Building | Start Date | End Date |
1 | 50 | 12/2/2024 | 12/18/2024 |
2 | 56 | 12/16/2024 | 1/3/2025 |
3 | 74 | 1/6/2025 | 1/22/2025 |
4 | 86 | 1/20/2025 | 2/5/2025 |
5 | 92 | 2/3/2025 | 2/19/2025 |
6 | 98 | 2/17/2025 | 3/5/2025 |
For questions, please contact management.